Construction Regulations, 2014
491 rows
| Verified | Citation | Number | Subs | Para | Subpara | Item | Role | Text |
|---|---|---|---|---|---|---|---|---|
| – | Construction Regulations 1 | 1 | opening | In these Regulations any word or expression to which a meaning has been assigned in the Act shall have the meaning so assigned and, unless the context otherwise indicates— | ||||
| – | Construction Regulations 2(1) | 2 | (1) | entry | These Regulations are applicable to all persons involved in construction work. | |||
| – | Construction Regulations 2(2) | 2 | (2) | entry | Regulations 3 and 5 are not applicable where the construction work carried out is in relation to a single storey dwelling for a client who intends to reside in such dwelling upon completion thereof. | |||
| – | Construction Regulations 3(1) | 3 | (1) | opening | A client who intends to have construction work carried out, must at least 30 days before that work is to be carried out apply to the provincial director in writing for a construction work permit to perform construction work if the intended construction work will— | |||
| – | Construction Regulations 3(1)(a) | 3 | (1) | (a) | entry | exceed 180 days; | ||
| – | Construction Regulations 3(1)(b) | 3 | (1) | (b) | entry | will involve more than 1800 person days of construction work; or | ||
| – | Construction Regulations 3(1)(c) | 3 | (1) | (c) | entry | the works contract is of a value equal to or exceeding thirteen million rand or Construction Industry Development Board (CIDB) grading level 6. | ||
| – | Construction Regulations 3(2) | 3 | (2) | entry | An application contemplated in subregulation (1) must be done in a form similar to Annexure 1. | |||
| – | Construction Regulations 3(3) | 3 | (3) | entry | The provincial director must issue a construction work permit in writing to perform construction work contemplated in subregulation (1) within 30 days of receiving the construction work permit application and must assign a site specific number for each construction site. | |||
| – | Construction Regulations 3(4) | 3 | (4) | entry | A site specific number contemplated in subregulation (3) must be conspicuously displayed at the main entrance to the site for which that number is assigned. | |||
| – | Construction Regulations 3(5) | 3 | (5) | opening | A construction work permit contemplated in this regulation may be granted only if— | |||
| – | Construction Regulations 3(5)(a) | 3 | (5) | (a) | entry | the fully completed documents contemplated in regulation 5 (1) (a) and (b) have been submitted; and | ||
| – | Construction Regulations 3(5)(b) | 3 | (5) | (b) | opening | proof in writing has been submitted— | ||
| – | Construction Regulations 3(5)(b)(i) | 3 | (5) | (b) | (i) | entry | that the client complies with regulation 5 (5) | |
| – | Construction Regulations 3(5)(b)(ii) | 3 | (5) | (b) | (ii) | entry | with regard to the registration and good standing of the principal contractor as contemplated in regulation 5 (1) (j); and | |
| – | Construction Regulations 3(5)(b)(iii) | 3 | (5) | (b) | (iii) | entry | that regulation 5 (1) (c), (d), (e), (g) and (h) has been complied with. | |
| – | Construction Regulations 3(6) | 3 | (6) | entry | A client must ensure that the principal contractor keeps a copy of the construction work permit contemplated in subregulation (1) in the occupational health and safety file for inspection by an inspector, the client, the client’s authorised agent, or an employee. | |||
| – | Construction Regulations 3(7) | 3 | (7) | entry | No construction work contemplated in subregulation (1) may be commenced or carried out before the construction work permit and number contemplated in subregulation (3) have been issued and assigned. | |||
| – | Construction Regulations 3(8) | 3 | (8) | entry | A site specific number contemplated in subregulation (3) is not transferrable. | |||
| – | Construction Regulations 4(1) | 4 | (1) | opening | A contractor who intends to carry out any construction work other than work contemplated in regulation 3 (1), must at least 7 days before that work is to be carried out notify the provincial director in writing in a form similar to Annexure 2 if the intended construction work will— | |||
| – | Construction Regulations 4(1)(a) | 4 | (1) | (a) | entry | include excavation work; | ||
| – | Construction Regulations 4(1)(b) | 4 | (1) | (b) | entry | include working at a height where there is risk of falling; | ||
| – | Construction Regulations 4(1)(c) | 4 | (1) | (c) | entry | include the demolition of a structure; or | ||
| – | Construction Regulations 4(1)(d) | 4 | (1) | (d) | entry | include the use of explosives to perform construction work. | ||
| – | Construction Regulations 4(2) | 4 | (2) | entry | A contractor who intends to carry out construction work that involves construction of a single storey dwelling for a client who is going to reside in such dwelling upon completion, must at least 7 days before that work is to be carried out notify the provincial director in writing in a form similar to Annexure 2 | |||
| – | Construction Regulations 5(1) | 5 | (1) | opening | A client must— | |||
| – | Construction Regulations 5(1)(a) | 5 | (1) | (a) | entry | prepare a baseline risk assessment for an intended construction work project; | ||
| – | Construction Regulations 5(1)(b) | 5 | (1) | (b) | entry | prepare a suitable, sufficiently documented and coherent site specific health and safety specification for the intended construction work based on the baseline risk assessment contemplated in paragraph (a); | ||
| – | Construction Regulations 5(1)(c) | 5 | (1) | (c) | entry | provide the designer with the health and safety specification contemplated in paragraph (b); | ||
| – | Construction Regulations 5(1)(d) | 5 | (1) | (d) | entry | ensure that the designer takes the prepared health and safety specification into consideration during the design stage; | ||
| – | Construction Regulations 5(1)(e) | 5 | (1) | (e) | entry | ensure that the designer carries out all responsibilities contemplated in regulation 6; | ||
| – | Construction Regulations 5(1)(f) | 5 | (1) | (f) | entry | include the health and safety specification in the tender documents; | ||
| – | Construction Regulations 5(1)(g) | 5 | (1) | (g) | entry | ensure that potential principal contractors submitting tenders have made adequate provision for the cost of health and safety measures; | ||
| – | Construction Regulations 5(1)(h) | 5 | (1) | (h) | entry | ensure that the principal contractor to be appointed has the necessary competencies and resources to carry out the construction work safely; | ||
| – | Construction Regulations 5(1)(i) | 5 | (1) | (i) | entry | take reasonable steps to ensure co-operation between all contractors appointed by the client to enable each of those contractors to comply with these Regulations; | ||
| – | Construction Regulations 5(1)(j) | 5 | (1) | (j) | entry | ensure before any work commences on a site that every principal contractor is registered and in good standing with the compensation fund or with a licensed compensation insurer as contemplated in the Compensation for Occupational Injuries and Diseases Act, 1993 (Act No. 130 of 1993); | ||
| – | Construction Regulations 5(1)(k) | 5 | (1) | (k) | entry | appoint every principal contractor in writing for the project or part thereof on the construction site; | ||
| – | Construction Regulations 5(1)(l) | 5 | (1) | (l) | entry | discuss and negotiate with the principal contractor the contents of the principal contractor’s health and safety plan contemplated in regulation 7 (1), and must thereafter finally approve that plan for implementation; | ||
| – | Construction Regulations 5(1)(m) | 5 | (1) | (m) | entry | ensure that a copy of the principal contractor’s health and safety plan is available on request to an employee, inspector or contractor; | ||
| – | Construction Regulations 5(1)(n) | 5 | (1) | (n) | entry | take reasonable steps to ensure that each contractor’s health and safety plan contemplated in regulation 7 (1) (a) is implemented and maintained; | ||
| – | Construction Regulations 5(1)(o) | 5 | (1) | (o) | entry | ensure that periodic health and safety audits and document verification are conducted at intervals mutually agreed upon between the principal contractor and any contractor, but at least once every 30 days; | ||
| – | Construction Regulations 5(1)(p) | 5 | (1) | (p) | entry | ensure that a copy of the health and safety audit report contemplated in paragraph (o) is provided to the principal contractor within seven days after the audit; | ||
| – | Construction Regulations 5(1)(q) | 5 | (1) | (q) | entry | stop any contractor from executing a construction activity which poses a threat to the health and safety of persons which is not in accordance with the client’s health and safety specifications and the principal contractor’s health and safety plan for the site; | ||
| – | Construction Regulations 5(1)(r) | 5 | (1) | (r) | entry | where changes are brought about to the design or construction work, make sufficient health and safety information and appropriate resources available to the principal contractor to execute the work safely; and | ||
| – | Construction Regulations 5(1)(s) | 5 | (1) | (s) | entry | ensure that the health and safety file contemplated in regulation 7 (1) (b) is kept and maintained by the principal contractor. | ||
| – | Construction Regulations 5(2) | 5 | (2) | entry | Where a client requires additional work to be performed as a result of a design change or an error in construction due to the actions of the client, the client must ensure that sufficient safety information and appropriate additional resources are available to execute the required work safely. | |||
| – | Construction Regulations 5(3) | 5 | (3) | entry | Where a fatality or permanent disabling injury occurs on a construction site, the client must ensure that the contractor provides the provincial director with a report contemplated in section 24 of the Act, in accordance with regulations 8 and 9 of the General Administrative Regulations, 2013, and that the report includes the measures that the contractor intends to implement to ensure a safe construction site as far as is reasonably practicable. | |||
| – | Construction Regulations 5(4) | 5 | (4) | entry | Where more than one principal contractor is appointed as contemplated in subregulation (1) (k), the client must take reasonable steps to ensure co-operation between all principal contactors and contractors in order to ensure compliance with these Regulations. | |||
| – | Construction Regulations 5(5) | 5 | (5) | entry | Where a construction work permit is required as contemplated in regulation 3 (1), the client must, without derogating from his or her health and safety responsibilities or liabilities, appoint a competent person in writing as an agent to act as his or her representative, and where such an appointment is made the duties that are imposed by these Regulations upon a client, apply as far as reasonably practicable to the agent so appointed. | |||
| – | Construction Regulations 5(6) | 5 | (6) | entry | Where notification of construction work is required as contemplated in regulation 4 (1), the client may, without derogating from his or her health and safety responsibilities or liabilities, appoint a competent person in writing as an agent to act as his or her representative, and where such an appointment is made the duties that are imposed by these Regulations upon a client, apply as far as reasonably practicable to the agent so appointed: | |||
| – | Construction Regulations 5(6) | 5 | (6) | proviso | Provided that, where the question arises as to whether an agent is necessary, the decision of an inspector is decisive. | |||
| – | Construction Regulations 5(7) | 5 | (7) | opening | An agent contemplated in subregulations (5) and (6) must— | |||
| – | Construction Regulations 5(7)(a) | 5 | (7) | (a) | entry | manage the health and safety on a construction project for the client; and | ||
| – | Construction Regulations 5(7)(b) | 5 | (7) | (b) | entry | be registered with a statutory body approved by the Chief Inspector as qualified to perform the required functions; | ||
| – | Construction Regulations 5(8) | 5 | (8) | entry | When the chief inspector has approved a statutory body as contemplated in subregulation (7) (b), he or she must give notice of that approval in the Gazette. | |||
| – | Construction Regulations 6(1) | 6 | (1) | opening | The designer of a structure must— | |||
| – | Construction Regulations 6(1)(a) | 6 | (1) | (a) | entry | ensure that the applicable safety standards incorporated into these Regulations under section 44 of the Act are complied with in the design; | ||
| – | Construction Regulations 6(1)(b) | 6 | (1) | (b) | entry | take into consideration the health and safety specification submitted by the client; | ||
| – | Construction Regulations 6(1)(c) | 6 | (1) | (c) | opening | before the contract is put out to tender, make available in a report to the client— | ||
| – | Construction Regulations 6(1)(c)(i) | 6 | (1) | (c) | (i) | entry | all relevant health and safety information about the design of the relevant structure that may affect the pricing of the construction work; | |
| – | Construction Regulations 6(1)(c)(ii) | 6 | (1) | (c) | (ii) | entry | the geotechnical-science aspects, where appropriate; and | |
| – | Construction Regulations 6(1)(c)(iii) | 6 | (1) | (c) | (iii) | entry | the loading that the structure is designed to withstand; | |
| – | Construction Regulations 6(1)(d) | 6 | (1) | (d) | entry | inform the client in writing of any known or anticipated dangers or hazards relating to the construction work, and make available all relevant information required for the safe execution of the work upon being designed or when the design is subsequently altered; | ||
| – | Construction Regulations 6(1)(e) | 6 | (1) | (e) | entry | refrain from including anything in the design of the structure necessitating the use of dangerous procedures or materials hazardous to the health and safety of persons, which can be avoided by modifying the design or by substituting materials; | ||
| – | Construction Regulations 6(1)(f) | 6 | (1) | (f) | entry | take into account the hazards relating to any subsequent maintenance of the relevant structure and must make provision in the design for that work to be performed to minimize the risk; | ||
| – | Construction Regulations 6(1)(g) | 6 | (1) | (g) | entry | when mandated by the client to do so, carry out the necessary inspections at appropriate stages to verify that the construction of the relevant structure is carried out in accordance with his design: | ||
| – | Construction Regulations 6(1)(g) | 6 | (1) | (g) | proviso | Provided that if the designer is not so mandated, the client’s appointed agent in this regard is responsible to carry out such inspections; | ||
| – | Construction Regulations 6(1)(h) | 6 | (1) | (h) | entry | when mandated as contemplated in paragraph (g), stop any contractor from executing any construction work which is not in accordance with the relevant design’s health and safety aspects: | ||
| – | Construction Regulations 6(1)(h) | 6 | (1) | (h) | proviso | Provided that if the designer is not so mandated, the client’s appointed agent in that regard must stop that contractor from executing that construction work; | ||
| – | Construction Regulations 6(1)(i) | 6 | (1) | (i) | entry | when mandated as contemplated in paragraph (g), in his or her final inspection of the completed structure in accordance with the National Building Regulations, include the health and safety aspects of the structure as far as reasonably practicable, declare the structure safe for use, and issue a completion certificate to the client and a copy thereof to the contractor; and | ||
| – | Construction Regulations 6(1)(j) | 6 | (1) | (j) | entry | during the design stage, take cognisance of ergonomic design principles in order to minimize ergonomic related hazards in all phases of the life cycle of a structure. | ||
| – | Construction Regulations 6(2) | 6 | (2) | opening | The designer of temporary works must ensure that— | |||
| – | Construction Regulations 6(2)(a) | 6 | (2) | (a) | entry | all temporary works are adequately designed so that it will be capable of supporting all anticipated vertical and lateral loads that may be applied; | ||
| – | Construction Regulations 6(2)(b) | 6 | (2) | (b) | entry | the designs of temporary works are done with close reference to the structural design drawings issued by the contractor, and in the event of any uncertainty consult the contractor; | ||
| – | Construction Regulations 6(2)(c) | 6 | (2) | (c) | entry | all drawings and calculations pertaining to the design of temporary works are kept at the office of the temporary works designer and are made available on request by an inspector; and | ||
| – | Construction Regulations 6(2)(d) | 6 | (2) | (d) | entry | the loads caused by the temporary works and any imposed loads are clearly indicated in the design. | ||
| – | Construction Regulations 7(1) | 7 | (1) | opening | A principal contractor must— | |||
| – | Construction Regulations 7(1)(a) | 7 | (1) | (a) | entry | provide and demonstrate to the client a suitable, sufficiently documented and coherent site specific health and safety plan, based on the client’s documented health and safety specifications contemplated in regulation 5 (1) (b), which plan must be applied from the date of commencement of and for the duration of the construction work and which must be reviewed and updated by the principal contractor as work progresses; | ||
| – | Construction Regulations 7(1)(b) | 7 | (1) | (b) | entry | open and keep on site a health and safety file, which must include all documentation required in terms of the Act and these Regulations, which must be made available on request to an inspector, the client, the client’s agent or a contractor; and | ||
| – | Construction Regulations 7(1)(c) | 7 | (1) | (c) | opening | on appointing any other contractor, in order to ensure compliance with the provisions of the Act— | ||
| – | Construction Regulations 7(1)(c)(i) | 7 | (1) | (c) | (i) | entry | provide contractors who are tendering to perform construction work for the principal contractor, with the relevant sections of the health and safety specifications contemplated in regulation 5 (1) (b) pertaining to the construction work which has to be performed; | |
| – | Construction Regulations 7(1)(c)(ii) | 7 | (1) | (c) | (ii) | entry | ensure that potential contractors submitting tenders have made sufficient provision for health and safety measures during the construction process; | |
| – | Construction Regulations 7(1)(c)(iii) | 7 | (1) | (c) | (iii) | entry | ensure that no contractor is appointed to perform construction work unless the principal contractor is reasonably satisfied that the contractor that he or she intends to appoint, has the necessary competencies and resources to perform the construction work safely; | |
| – | Construction Regulations 7(1)(c)(iv) | 7 | (1) | (c) | (iv) | entry | ensure prior to work commencing on the site that every contractor is registered and in good standing with the compensation fund or with a licensed compensation insurer as contemplated in the Compensation for Occupational Injuries and Diseases Act, 1993; | |
| – | Construction Regulations 7(1)(c)(v) | 7 | (1) | (c) | (v) | entry | appoint each contractor in writing for the part of the project on the construction site; | |
| – | Construction Regulations 7(1)(c)(vi) | 7 | (1) | (c) | (vi) | entry | take reasonable steps to ensure that each contractor’s health and safety plan contemplated in subregulation (2) (a) is implemented and maintained on the construction site; | |
| – | Construction Regulations 7(1)(c)(vii) | 7 | (1) | (c) | (vii) | entry | ensure that the periodic site audits and document verification are conducted at intervals mutually agreed upon between the principal contractor and any contractor, but at least once every 30 days; | |
| – | Construction Regulations 7(1)(c)(viii) | 7 | (1) | (c) | (viii) | entry | stop any contractor from executing construction work which is not in accordance with the client’s health and safety specifications and the principal contractor’s health and safety plan for the site or which poses a threat to the health and safety of persons; | |
| – | Construction Regulations 7(1)(c)(ix) | 7 | (1) | (c) | (ix) | entry | where changes are brought about to the design and construction, make available sufficient health and safety information and appropriate resources to the contractor to execute the work safely; and | |
| – | Construction Regulations 7(1)(c)(x) | 7 | (1) | (c) | (x) | entry | discuss and negotiate with the contractor the contents of the health and safety plan contemplated in subregulation (2) (a), and must thereafter finally approve that plan for implementation; | |
| – | Construction Regulations 7(1)(d) | 7 | (1) | (d) | entry | ensure that a copy of his or her health and safety plan contemplated in paragraph (a), as well as the contractor’s health and safety plan contemplated in subregulation (2) (a), is available on request to an employee, an inspector, a contractor, the client or the client’s agent; | ||
| – | Construction Regulations 7(1)(e) | 7 | (1) | (e) | entry | hand over a consolidated health and safety file to the client upon completion of the construction work and must, in addition to the documentation referred to in subregulation (2) (b), include a record of all drawings, designs, materials used and other similar information concerning the completed structure; | ||
| – | Construction Regulations 7(1)(f) | 7 | (1) | (f) | entry | in addition to the documentation required in the health and safety file in terms of paragraph (c) (v) and subregulation (2) (b), include and make available a comprehensive and updated list of all the contractors on site accountable to the principal contractor, the agreements between the parties and the type of work being done; and | ||
| – | Construction Regulations 7(1)(g) | 7 | (1) | (g) | entry | ensure that all his or her employees have a valid medical certificate of fitness specific to the construction work to be performed and issued by an occupational health practitioner in the form of Annexure 3. | ||
| – | Construction Regulations 7(2) | 7 | (2) | opening | A contractor must prior to performing any construction work— | |||
| – | Construction Regulations 7(2)(a) | 7 | (2) | (a) | entry | provide and demonstrate to the principal contractor a suitable and sufficiently documented health and safety plan, based on the relevant sections of the client’s health and safety specification contemplated in regulation 5 (1) (b) and provided by the principal contractor in terms of subregulation (1) (a), which plan must be applied from the date of commencement of and for the duration of the construction work and which must be reviewed and updated by the contractor as work progresses; | ||
| – | Construction Regulations 7(2)(b) | 7 | (2) | (b) | entry | open and keep on site a health and safety file, which must include all documentation required in terms of the Act and these Regulations, and which must be made available on request to an inspector, the client, the client’s agent or the principal contractor; | ||
| – | Construction Regulations 7(2)(c) | 7 | (2) | (c) | entry | before appointing another contractor to perform construction work be reasonably satisfied that the contractor that he or she intends to appoint has the necessary competencies and resources to perform the construction work safely; | ||
| – | Construction Regulations 7(2)(d) | 7 | (2) | (d) | entry | co-operate with the principal contractor as far as is necessary to enable each of them to comply with the provisions of the Act; and | ||
| – | Construction Regulations 7(2)(e) | 7 | (2) | (e) | entry | as far as is reasonably practicable, promptly provide the principal contractor with any information which might affect the health and safety of any person at work carrying out construction work on the site, any person who might be affected by the work of such a person at work, or which might justify a review of the health and safety plan. | ||
| – | Construction Regulations 7(3) | 7 | (3) | entry | Where a contractor appoints another contractor to perform construction work, the duties determined in sub-regulation (1) (b) to (g) that apply to the principal contractor apply to the contractor as if he or she were the principal contractor. | |||
| – | Construction Regulations 7(4) | 7 | (4) | entry | A principal contractor must take reasonable steps to ensure co-operation between all contractors appointed by the principal contractor to enable each of those contractors to comply with these Regulations. | |||
| – | Construction Regulations 7(5) | 7 | (5) | entry | No contractor may allow or permit any employee or person to enter any site, unless that employee or person has undergone health and safety induction training pertaining to the hazards prevalent on the site at the time of entry. | |||
| – | Construction Regulations 7(6) | 7 | (6) | entry | A contractor must ensure that all visitors to a construction site undergo health and safety induction pertaining to the hazards prevalent on the site and must ensure that such visitors have the necessary personal protective equipment. | |||
| – | Construction Regulations 7(7) | 7 | (7) | entry | A contractor must at all times keep on his or her construction site records of the health and safety induction training contemplated in subregulation (6) and such records must be made available on request to an inspector, the client, the client’s agent or the principal contractor. | |||
| – | Construction Regulations 7(8) | 7 | (8) | entry | A contractor must ensure that all his or her employees have a valid medical certificate of fitness specific to the construction work to be performed and issued by an occupational health practitioner in the form of Annexure 3. | |||
| – | Construction Regulations 8(1) | 8 | (1) | entry | A principal contractor must in writing appoint one full-time competent person as the construction manager with the duty of managing all the construction work on a single site, including the duty of ensuring occupational health and safety compliance, and in the absence of the construction manager an alternate must be appointed by the principal contractor. | |||
| – | Construction Regulations 8(2) | 8 | (2) | entry | A principal contractor must upon having considered the size of the project, in writing appoint one or more assistant construction managers for different sections thereof: | |||
| – | Construction Regulations 8(2) | 8 | (2) | proviso | Provided that the designation of any such person does not relieve the construction manager of any personal accountability for failing in his or her management duties in terms of this regulation. | |||
| – | Construction Regulations 8(3) | 8 | (3) | entry | Where the construction manager has not appointed assistant construction managers as contemplated in subregulation (2), or, in the opinion of an inspector, a sufficient number of such assistant construction managers have not been appointed, that inspector must direct the construction manager in writing to appoint the number of assistant construction managers indicated by the inspector, and those assistant construction managers must be regarded as having been appointed under subregulation (2). | |||
| – | Construction Regulations 8(4) | 8 | (4) | entry | No construction manager appointed under subregulation (1) may manage any construction work on or in any construction site other than the site in respect of which he or she has been appointed. | |||
| – | Construction Regulations 8(5) | 8 | (5) | entry | A contractor must, after consultation with the client and having considered the size of the project, the degree of danger likely to be encountered or the accumulation of hazards or risks on the site, appoint a full-time or part-time construction health and safety officer in writing to assist in the control of all health and safety related aspects on the site: | |||
| – | Construction Regulations 8(5) | 8 | (5) | proviso | Provided that, where the question arises as to whether a construction health and safety officer is necessary, the decision of an inspector is decisive. | |||
| – | Construction Regulations 8(6) | 8 | (6) | entry | No contractor may appoint a construction health and safety officer to assist in the control of health and safety related aspects on the site unless he or she is reasonably satisfied that the construction health and safety officer that he or she intends to appoint is registered with a statutory body approved by the Chief Inspector and has necessary competencies and resources to assist the contractor | |||
| – | Construction Regulations 8(7) | 8 | (7) | entry | A construction manager must in writing appoint construction supervisors responsible for construction activities and ensuring occupational health and safety compliance on the construction site. | |||
| – | Construction Regulations 8(8) | 8 | (8) | entry | A contractor must, upon having considered the size of the project, in writing appoint one or more competent employees for different sections thereof to assist the construction supervisor contemplated in subregulation (7), and every such employee has, to the extent clearly defined by the contractor in the letter of appointment, the same duties as the construction supervisor: | |||
| – | Construction Regulations 8(8) | 8 | (8) | proviso | Provided that the designation of any such employee does not relieve the construction supervisor of any personal accountability for failing in his or her supervisory duties in terms of this regulation. | |||
| – | Construction Regulations 8(9) | 8 | (9) | entry | Where the contractor has not appointed an employee as contemplated in subregulation (8), or, in the opinion of an inspector, a sufficient number of such employees have not been appointed, that inspector must instruct the employer to appoint the number of employees indicated by the inspector, and those employees must be regarded as having been appointed under subregulation (8). | |||
| – | Construction Regulations 8(10) | 8 | (10) | entry | No construction supervisor appointed under subregulation (7) may supervise any construction work on or in any construction site other than the site in respect of which he or she has been appointed: | |||
| – | Construction Regulations 8(10) | 8 | (10) | proviso | Provided that if a sufficient number of competent employees have been appropriately designated under subregulation (7) on all the relevant construction sites, the appointed construction supervisor may supervise more than one site. | |||
| – | Construction Regulations 9(1) | 9 | (1) | opening | A contractor must, before the commencement of any construction work and during such construction work, have risk assessments performed by a competent person appointed in writing, which risk assessments form part of the health and safety plan to be applied on the site, and must include— | |||
| – | Construction Regulations 9(1)(a) | 9 | (1) | (a) | entry | the identification of the risks and hazards to which persons may be exposed to; | ||
| – | Construction Regulations 9(1)(b) | 9 | (1) | (b) | entry | an analysis and evaluation of the risks and hazards identified based on a documented method; | ||
| – | Construction Regulations 9(1)(c) | 9 | (1) | (c) | entry | a documented plan and applicable safe work procedures to mitigate, reduce or control the risks and hazards that have been identified; | ||
| – | Construction Regulations 9(1)(d) | 9 | (1) | (d) | entry | a monitoring plan; and | ||
| – | Construction Regulations 9(1)(e) | 9 | (1) | (e) | entry | a review plan | ||
| – | Construction Regulations 9(2) | 9 | (2) | entry | A contractor must ensure that as far as is reasonably practicable, ergonomic related hazards are analyzed, evaluated and addressed in a risk assessment. | |||
| – | Construction Regulations 9(3) | 9 | (3) | entry | A contractor must ensure that all employees under his or her control are informed, instructed and trained by a competent person regarding any hazard and the related work procedures and or control measures before any work commences, and thereafter at the times determined in the risk assessment monitoring and review plan of the relevant site. | |||
| – | Construction Regulations 9(4) | 9 | (4) | entry | A principal contractor must ensure that all contractors are informed regarding any hazard that is stipulated in the risk assessment before any work commences, and thereafter at the times that may be determined in the risk assessment monitoring and review plan of the relevant site. | |||
| – | Construction Regulations 9(5) | 9 | (5) | entry | A contractor must consult with the health and safety committee or, if no health and safety committee exists, with a representative trade union or representative group of employees, on the monitoring and review of the risk assessments of the relevant site. | |||
| – | Construction Regulations 9(6) | 9 | (6) | entry | A contractor must ensure that copies of the risk assessments of the relevant site are available on site for inspection by an inspector, the client, the client’s agent, any contractor, any employee, a representative trade union, a health and safety representative or any member of the health and safety committee. | |||
| – | Construction Regulations 9(7) | 9 | (7) | opening | A contractor must review the relevant risk assessment— | |||
| – | Construction Regulations 9(7)(a) | 9 | (7) | (a) | entry | where changes are effected to the design and or construction that result in a change to the risk profile; or | ||
| – | Construction Regulations 9(7)(b) | 9 | (7) | (b) | entry | when an incident has occurred. | ||
| – | Construction Regulations 10(1) | 10 | (1) | opening | A contractor must— | |||
| – | Construction Regulations 10(1)(a) | 10 | (1) | (a) | entry | designate a competent person to be responsible for the preparation of a fall protection plan; | ||
| – | Construction Regulations 10(1)(b) | 10 | (1) | (b) | entry | ensure that the fall protection plan contemplated in paragraph (a) is implemented, amended where and when necessary and maintained as required; and | ||
| – | Construction Regulations 10(1)(c) | 10 | (1) | (c) | entry | take steps to ensure continued adherence to the fall protection plan. | ||
| – | Construction Regulations 10(2) | 10 | (2) | opening | A fall protection plan contemplated in subregulation (1), must include— | |||
| – | Construction Regulations 10(2)(a) | 10 | (2) | (a) | entry | a risk assessment of all work carried out from a fall risk position and the procedures and methods used to address all the risks identified per location; | ||
| – | Construction Regulations 10(2)(b) | 10 | (2) | (b) | entry | the processes for the evaluation of the employees’ medical fitness necessary to work at a fall risk position and the records thereof; | ||
| – | Construction Regulations 10(2)(c) | 10 | (2) | (c) | entry | a programme for the training of employees working from a fall risk position and the records thereof; | ||
| – | Construction Regulations 10(2)(d) | 10 | (2) | (d) | entry | the procedure addressing the inspection, testing and maintenance of all fall protection equipment; and | ||
| – | Construction Regulations 10(2)(e) | 10 | (2) | (e) | entry | a rescue plan detailing the necessary procedure, personnel and suitable equipment required to affect a rescue of a person in the event of a fall incident to ensure that the rescue procedure is implemented immediately following the incident. | ||
| – | Construction Regulations 10(3) | 10 | (3) | entry | A contractor must ensure that a construction manager appointed under regulation 8 (1) is in possession of the most recently updated version of the fall protection plan. | |||
| – | Construction Regulations 10(4) | 10 | (4) | opening | A contractor must ensure that— | |||
| – | Construction Regulations 10(4)(a) | 10 | (4) | (a) | entry | all unprotected openings in floors, edges, slabs, hatchways and stairways are adequately guarded, fenced or barricaded or that similar means are used to safeguard any person from falling through such openings; | ||
| – | Construction Regulations 10(4)(b) | 10 | (4) | (b) | entry | no person is required to work in a fall risk position, unless such work is performed safely as contemplated in subregulation (2); | ||
| – | Construction Regulations 10(4)(c) | 10 | (4) | (c) | opening | fall prevention and fall arrest equipment are— | ||
| – | Construction Regulations 10(4)(c)(i) | 10 | (4) | (c) | (i) | entry | approved as suitable and of sufficient strength for the purpose for which they are being used, having regard to the work being carried out and the load, including any person, they are intended to bear; and | |
| – | Construction Regulations 10(4)(c)(ii) | 10 | (4) | (c) | (ii) | entry | securely attached to a structure or plant, and the structure or plant and the means of attachment thereto are suitable and of sufficient strength and stability for the purpose of safely supporting the equipment and any person who could fall; and | |
| – | Construction Regulations 10(4)(d) | 10 | (4) | (d) | entry | fall arrest equipment is used only where it is not reasonably practicable to use fall prevention equipment. | ||
| – | Construction Regulations 10(5) | 10 | (5) | opening | Where roof work is being performed on a construction site, the contractor must ensure that, in addition to the requirements set out in subregulations (2) and (4), it is indicated in the fall protection plan that— | |||
| – | Construction Regulations 10(5)(a) | 10 | (5) | (a) | entry | the roof work has been properly planned; | ||
| – | Construction Regulations 10(5)(b) | 10 | (5) | (b) | entry | the roof erectors are competent to carry out the work; | ||
| – | Construction Regulations 10(5)(c) | 10 | (5) | (c) | entry | no employee is permitted to work on roofs during inclement weather conditions or if any conditions are hazardous to the health and safety of the employee; | ||
| – | Construction Regulations 10(5)(d) | 10 | (5) | (d) | entry | all covers to openings and fragile material are of sufficient strength to withstand any imposed loads; | ||
| – | Construction Regulations 10(5)(e) | 10 | (5) | (e) | entry | suitable and sufficient platforms, coverings or other similar means of support have been provided to be used in such a way that the weight of any person passing across or working on or from fragile material is supported; and | ||
| – | Construction Regulations 10(5)(f) | 10 | (5) | (f) | entry | suitable and sufficient guard-rails, barriers and toe-boards or other similar means of protection prevent, as far as is reasonably practicable, the fall of any person, material or equipment. | ||
| – | Construction Regulations 11(1) | 11 | (1) | opening | A contractor must ensure that— | |||
| – | Construction Regulations 11(1)(a) | 11 | (1) | (a) | entry | all reasonably practicable steps are taken to prevent the uncontrolled collapse of any new or existing structure or any part thereof, which may become unstable or is in a temporary state of weakness or instability due to the carrying out of construction work; | ||
| – | Construction Regulations 11(1)(b) | 11 | (1) | (b) | entry | no structure or part of a structure is loaded in a manner which would render it unsafe; and | ||
| – | Construction Regulations 11(1)(c) | 11 | (1) | (c) | entry | all drawings pertaining to the design of the relevant structure are kept on site and are available on request to an inspector, other contractors, the client and the client’s agent or employee. | ||
| – | Construction Regulations 11(2) | 11 | (2) | opening | An owner of a structure must ensure that— | |||
| – | Construction Regulations 11(2)(a) | 11 | (2) | (a) | entry | inspections of that structure are carried out periodically by competent persons in order to render the structure safe for continued use; | ||
| – | Construction Regulations 11(2)(b) | 11 | (2) | (b) | entry | that the inspections contemplated in paragraph (a) are carried out at least once every six months for the first two years and thereafter yearly; | ||
| – | Construction Regulations 11(2)(c) | 11 | (2) | (c) | entry | the structure is maintained in such a manner that it remains safe for continued use; | ||
| – | Construction Regulations 11(2)(d) | 11 | (2) | (d) | entry | the records of inspections and maintenance are kept and made available on request to an inspector. | ||
| – | Construction Regulations 12(1) | 12 | (1) | entry | A contractor must appoint a temporary works designer in writing to design, inspect and approve the erected temporary works on site before use. | |||
| – | Construction Regulations 12(2) | 12 | (2) | entry | A contractor must ensure that all temporary works operations are carried out under the supervision of a competent person who has been appointed in writing for that purpose. | |||
| – | Construction Regulations 12(3) | 12 | (3) | opening | A contractor must ensure that— | |||
| – | Construction Regulations 12(3)(a) | 12 | (3) | (a) | entry | all temporary works structures are adequately erected, supported, braced and maintained by a competent person so that they are capable of supporting all anticipated vertical and lateral loads that may be applied to them, and that no loads are imposed onto the structure that the structure is not designed to withstand; | ||
| – | Construction Regulations 12(3)(b) | 12 | (3) | (b) | entry | all temporary works structures are done with close reference to the structural design drawings, and where any uncertainty exists the structural designer should be consulted; | ||
| – | Construction Regulations 12(3)(c) | 12 | (3) | (c) | entry | detailed activity specific drawings pertaining to the design of temporary works structures are kept on the site and are available on request to an inspector, other contractors, the client, the client’s agent or any employee; | ||
| – | Construction Regulations 12(3)(d) | 12 | (3) | (d) | entry | all persons required to erect, move or dismantle temporary works structures are provided with adequate training and instruction to perform those operations safely; | ||
| – | Construction Regulations 12(3)(e) | 12 | (3) | (e) | entry | all equipment used in temporary works structure are carefully examined and checked for suitability by a competent person, before being used; | ||
| – | Construction Regulations 12(3)(f) | 12 | (3) | (f) | entry | all temporary works structures are inspected by a competent person immediately before, during and after the placement of concrete, after inclement weather or any other imposed load and at least on a daily basis until the temporary works structure has been removed and the results have been recorded in a register and made available on site; | ||
| – | Construction Regulations 12(3)(g) | 12 | (3) | (g) | entry | no person may cast concrete, until authorization in writing has been given by the competent person contemplated in paragraph (a); | ||
| – | Construction Regulations 12(3)(h) | 12 | (3) | (h) | entry | if, after erection, any temporary works structure is found to be damaged or weakened to such a degree that its integrity is affected, it is safely removed or reinforced immediately; | ||
| – | Construction Regulations 12(3)(i) | 12 | (3) | (i) | opening | adequate precautionary measures are taken in order to— | ||
| – | Construction Regulations 12(3)(i)(i) | 12 | (3) | (i) | (i) | entry | secure any deck panels against displacement; and | |
| – | Construction Regulations 12(3)(i)(ii) | 12 | (3) | (i) | (ii) | entry | prevent any person from slipping on temporary works due to the application of release agents; | |
| – | Construction Regulations 12(3)(j) | 12 | (3) | (j) | entry | as far as is reasonably practicable, the health of any person is not affected through the use of solvents or oils or any other similar substances; | ||
| – | Construction Regulations 12(3)(k) | 12 | (3) | (k) | entry | upon casting concrete, the temporary works structure is left in place until the concrete has acquired sufficient strength to safely support its own weight and any imposed load, and is not removed until authorization in writing has been given by the competent person contemplated in paragraph (a); | ||
| – | Construction Regulations 12(3)(l) | 12 | (3) | (l) | entry | the foundation conditions are suitable to withstand the loads caused by the temporary works structure and any imposed load in accordance with the temporary works design. | ||
| – | Construction Regulations 12(3)(m) | 12 | (3) | (m) | entry | provision is made for safe access by means of secured ladders or staircases for all work to be carried out above the foundation bearing level; | ||
| – | Construction Regulations 12(3)(n) | 12 | (3) | (n) | entry | a temporary works drawing or any other relevant document includes construction sequences and methods statements; | ||
| – | Construction Regulations 12(3)(o) | 12 | (3) | (o) | entry | the temporary works designer has been issued with the latest revision of any relevant structural design drawing; | ||
| – | Construction Regulations 12(3)(p) | 12 | (3) | (p) | entry | a temporary works design and drawing is used only for its intended purpose and for a specific portion of a construction site; and | ||
| – | Construction Regulations 12(3)(q) | 12 | (3) | (q) | entry | the temporary works drawings are approved by the temporary works designer before the erection of any temporary works. | ||
| – | Construction Regulations 12(4) | 12 | (4) | entry | No contractor may use a temporary works design and drawing for any work other than its intended purpose. | |||
| – | Construction Regulations 13(1) | 13 | (1) | opening | A contractor must— | |||
| – | Construction Regulations 13(1)(a) | 13 | (1) | (a) | entry | ensure that all excavation work is carried out under the supervision of a competent person who has been appointed in writing for that purpose; and | ||
| – | Construction Regulations 13(1)(b) | 13 | (1) | (b) | entry | evaluate, as far as is reasonably practicable, the stability of the ground before excavation work begins. | ||
| – | Construction Regulations 13(2) | 13 | (2) | opening | A contractor who performs excavation work— | |||
| – | Construction Regulations 13(2)(a) | 13 | (2) | (a) | entry | must take reasonable and sufficient steps in order to prevent, as far as is reasonably practicable, any person from being buried or trapped by a fall or dislodgement of material in an excavation; | ||
| – | Construction Regulations 13(2)(b) | 13 | (2) | (b) | opening | may not require or permit any person to work in an excavation which has not been adequately shored or braced: | ||
| – | Construction Regulations 13(2)(b) | 13 | (2) | (b) | proviso | Provided that shoring and bracing may not be necessary where— | ||
| – | Construction Regulations 13(2)(b)(i) | 13 | (2) | (b) | (i) | entry | the sides of the excavation are sloped to at least the maximum angle of repose measured relative to the horizontal plane; or | |
| – | Construction Regulations 13(2)(b)(ii) | 13 | (2) | (b) | (ii) | opening | such an excavation is in stable material: |