Construction Regulations 3 Application for construction work permit

16 rows

VerifiedCitationNumberSubsParaSubparaItemRoleText
Subsection (1)
–Construction Regulations 3(1)3(1)opening
A client who intends to have construction work carried out, must at least 30 days before that work is to be carried out apply to the provincial director in writing for a construction work permit to perform construction work if the intended construction work will—
–Construction Regulations 3(1)(a)3(1)(a)entry
exceed 180 days;
–Construction Regulations 3(1)(b)3(1)(b)entry
will involve more than 1800 person days of construction work; or
–Construction Regulations 3(1)(c)3(1)(c)entry
the works contract is of a value equal to or exceeding thirteen million rand or Construction Industry Development Board (CIDB) grading level 6.
Subsection (2)
–Construction Regulations 3(2)3(2)entry
An application contemplated in subregulation (1) must be done in a form similar to Annexure 1.
Subsection (3)
–Construction Regulations 3(3)3(3)entry
The provincial director must issue a construction work permit in writing to perform construction work contemplated in subregulation (1) within 30 days of receiving the construction work permit application and must assign a site specific number for each construction site.
Subsection (4)
–Construction Regulations 3(4)3(4)entry
A site specific number contemplated in subregulation (3) must be conspicuously displayed at the main entrance to the site for which that number is assigned.
Subsection (5)
–Construction Regulations 3(5)3(5)opening
A construction work permit contemplated in this regulation may be granted only if—
–Construction Regulations 3(5)(a)3(5)(a)entry
the fully completed documents contemplated in regulation 5 (1) (a) and (b) have been submitted; and
–Construction Regulations 3(5)(b)3(5)(b)opening
proof in writing has been submitted—
–Construction Regulations 3(5)(b)(i)3(5)(b)(i)entry
that the client complies with regulation 5 (5)
–Construction Regulations 3(5)(b)(ii)3(5)(b)(ii)entry
with regard to the registration and good standing of the principal contractor as contemplated in regulation 5 (1) (j); and
–Construction Regulations 3(5)(b)(iii)3(5)(b)(iii)entry
that regulation 5 (1) (c), (d), (e), (g) and (h) has been complied with.
Subsection (6)
–Construction Regulations 3(6)3(6)entry
A client must ensure that the principal contractor keeps a copy of the construction work permit contemplated in subregulation (1) in the occupational health and safety file for inspection by an inspector, the client, the client’s authorised agent, or an employee.
Subsection (7)
–Construction Regulations 3(7)3(7)entry
No construction work contemplated in subregulation (1) may be commenced or carried out before the construction work permit and number contemplated in subregulation (3) have been issued and assigned.
Subsection (8)
–Construction Regulations 3(8)3(8)entry
A site specific number contemplated in subregulation (3) is not transferrable.