Construction Regulations, 2014 › 14 Demolition work
Construction Regulations 14(2)
| ID | 1119 |
|---|---|
| Citation | Construction Regulations 14(2) |
| Instrument | Construction Regulations, 2014 |
| Instrument type | Regulation |
| Part | — |
| Number | 14 |
| Heading | Demolition work |
| Subsection | (2) |
| Paragraph | — |
| Subparagraph | — |
| Item | — |
| Text role | entry |
| Sort key | 06.0014.00020 |
| Source | GNR.84 of 7 February 2014 |
| Amended by | — |
| In force from | 2014-02-07 |
| Status | In force |
| Verified | Yes (2026-11-17) |
| Flag | — |
| Note | — |
| Text | A contractor must ensure that before any demolition work is carried out, and in order to ascertain the method of demolition to be used, a detailed structural engineering survey of the structure to be demolished is carried out by a competent person and that a method statement on the procedure to be followed in demolishing the structure is developed by that person. |