Construction Regulations, 2014 › 14 Demolition work

Construction Regulations 14(2)

ID1119
CitationConstruction Regulations 14(2)
InstrumentConstruction Regulations, 2014
Instrument typeRegulation
Part—
Number14
HeadingDemolition work
Subsection(2)
Paragraph—
Subparagraph—
Item—
Text roleentry
Sort key06.0014.00020
SourceGNR.84 of 7 February 2014
Amended by—
In force from2014-02-07
StatusIn force
VerifiedYes (2026-11-17)
Flag—
Note—
Text
A contractor must ensure that before any demolition work is carried out, and in order to ascertain the method of demolition to be used, a detailed structural engineering survey of the structure to be demolished is carried out by a competent person and that a method statement on the procedure to be followed in demolishing the structure is developed by that person.