Construction Regulations, 2014 › 14 Demolition work
Construction Regulations 14(11)
| ID | 1144 |
|---|---|
| Citation | Construction Regulations 14(11) |
| Instrument | Construction Regulations, 2014 |
| Instrument type | Regulation |
| Part | — |
| Number | 14 |
| Heading | Demolition work |
| Subsection | (11) |
| Paragraph | — |
| Subparagraph | — |
| Item | — |
| Text role | entry |
| Sort key | 06.0014.00270 |
| Source | GNR.84 of 7 February 2014 |
| Amended by | — |
| In force from | 2014-02-07 |
| Status | In force |
| Verified | No |
| Note | — |
| Text | Where the demolition work involves the use of explosives, a method statement must be developed in accordance with the applicable explosives legislation, by an appointed person who is competent in the use of explosives for demolition work and all persons involved in the demolition works must adhere to demolition procedures issued by the appointed person. |